Weire Ridge Adwa Asphalt Road project Weire Ridge Adwa Asphalt Road Status: Completed From Sep.2011-Mar.2022 Client: Ethiopian Roads Authority Location: Tigray Ethiopia home Tab 2 Weire Ridge Adwa Asphalt Road...
Finished projects
By : AKGC
Comments:
0
Likes:
0
Description Metu Multi- Purpose Hall በመቱ ከተማ እየተናቀቀ ያለው ዘርፍ ብዙ ህንጻ። Challenge Solution Result Challenge Solution Result Project ParticularsShare:Contractor::Alemayehu Ketema General ContractorClient::AKGCConsultant: Eng.:Joaw Consulting Architecting EnginerProject::Metu Multi- Purpose HallDate...
Share
By : AKGC
Comments:
0
Likes:
0
Description Our Company ALEMAYEHU KETEMA GENERAL CONTRACTOR (AKGC) entered a construction Contract agreement with the FDRE IRRIGATION DEVELOPMENT COMMISSION for the construction of Lot-1:- Welmel Weir and Feeder Canal Structure ...
Share
By : AKGC
Comments:
0
Likes:
0
Description Aleta Wondo -Daye Road Project is located in the south of Ethiopia the Oromia Regional State connecting Dodola and Nensebo Woredas. The project has a total length of 72.25Km...
Share
By : AKGC
Comments:
0
Likes:
0
Description Edo – Serofta ‐ Warka Road Project is located in the West Arsi Zone of the Oromia Regional State connecting Dodola and Nensebo Woredas. The project has a total...
Share
By : AKGC
Comments:
0
Likes:
0
Description Gilgel Bales Debate RR50 Road Project Description: Construction of Gilgel Beles Debate RR50 Project of new road of 58.039kms length consists of about 122,697 m3 of Gravel surface course,...
Share
By : AKGC
Comments:
0
Likes:
0
Description በመጠናቀቅ ላይ የሚገኘው የደራርቱ ቱሉ ስፖርት አካዳሚ ፕሮጀክት፣ (AKGC)/አ.ከ.ጠ ስራ ተቋራጭ እየሰራቸው ከሚገኘው ፕሮጀክቶች መካከል አንዱ ነው፡፡ የህ ፕሮጀክት የተለያዩ የህንፃ ብሎኮችን ያካተተ የስፖርት አካዳሚ ሲሆነ የአስተዳደር ብሎክ ክፍል፤...
Share
By : AKGC
Comments:
0
Likes:
0
Guder qanyi Dallasa Balami Goda Arba Wayu Road Project The near-completion of Guder qanyi Dallasa Balami Goda Arba Wayu Road Project (AKGC) is one of the projects being undertaken by...
Share
By : AKGC
Comments:
0
Likes:
0
Description Shashemene- Goba Road Project Contract 4, Shashemene-Dodola Junction Lot 2: Km 35 – Dodola Junction to DST Asphalt consisting of a large number of Earth works, Minor and Major...
Share
By : AKGC
Comments:
0
Likes:
0
Description Description: the construcción of Cultural Center and museum and the construction of site compound road complex construction. Value Completed and Certified was 22,116,371.50 Birr Commencement date 13/11/1994 Date of...
Share